Program Management Professional (PgMP) — Question 234
What is a stakeholder analysis chart?
Answer options
- A. It is a matrix that identifies who must communicate with whom.
- B. It is a matrix that documents the stakeholders' requirements, when the requirements were created, and when the fulfillment of the requirements took place.
- C. It is a matrix that documents stakeholders' threats, perceived threats, and communication needs.
- D. It is a matrix that identifies all of the stakeholders and to whom they must report to.
Correct answer: C
Explanation
The correct answer is C because a stakeholder analysis chart specifically focuses on documenting the threats and communication needs of stakeholders. Option A describes communication relationships, B outlines requirements and timelines, and D pertains to reporting structures, none of which capture the essence of stakeholder threats and needs.