Program Management Professional (PgMP) — Question 233
Which one of the following is not an output of the direct and manage program execution process?
Answer options
- A. Results of program work
- B. Program budget
- C. Change requests
- D. Request to terminate the program
Correct answer: B
Explanation
The correct answer is B, the Program budget, as it is typically established during the planning phase rather than being an output of the execution process. The other options, such as results of program work, change requests, and requests to terminate the program, are direct outputs resulting from managing the execution of the program.