Program Management Professional (PgMP) — Question 230

You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?

Answer options

Correct answer: B

Explanation

The correct answer is B, as requirements analysis is typically part of project management rather than a theme of program management. The other options, such as stakeholder management, benefits management, and program governance, are essential themes that guide the execution and success of programs.