Program Management Professional (PgMP) — Question 229

What project management term would you associated with a predetermined budget you're your program?

Answer options

Correct answer: B

Explanation

The correct answer is B, as a constraint refers to any limiting factor, including budgetary restrictions, that impacts project execution. While 'Cost baseline' (C) is related to budgeting, it specifically denotes the approved version of the project budget, not the general concept of limitations. 'Program governance' (A) and 'Assumption' (D) are not directly tied to predetermined budgets.