Program Management Professional (PgMP) — Question 217
Where are negative risks recorded?
Answer options
- A. Negative risk register
- B. Risk management plan
- C. Risk register
- D. Issues log
Correct answer: C
Explanation
The correct answer is C, as the Risk register is the official document used to track both positive and negative risks throughout the project. Options A and B are incorrect because a Negative risk register does not exist as a standard document, and the Risk management plan focuses more on the strategies and processes rather than on individual risks. Option D, Issues log, is intended for documenting issues that have already occurred, not potential risks.