Program Management Professional (PgMP) — Question 216
You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?
Answer options
- A. Stakeholder matrix
- B. Communications management plan
- C. Requirements traceability matrix
- D. Stakeholder registry
Correct answer: D
Explanation
The correct answer is D, the Stakeholder registry, as it is specifically designed to record stakeholders and their relevant information. The Stakeholder matrix (A) is used to analyze stakeholder influence and interest, while the Communications management plan (B) focuses on how communication will occur with stakeholders. The Requirements traceability matrix (C) tracks requirements throughout the project lifecycle, not stakeholder information.