Program Management Professional (PgMP) — Question 190
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?
Answer options
- A. Consider the option to close out the key project
- B. Evaluate the program and re-baseline the objectives
- C. Assess the benefits and impact to the program
- D. Amend the risk register with the key project changes
Correct answer: C
Explanation
The program manager should first assess the benefits and impacts of the change request on the overall program, as understanding these factors is crucial for informed decision-making. Closing the project or re-baselining objectives may not be necessary until the implications of the change are fully understood. Updating the risk register is important but comes after evaluating the potential impacts.