Program Management Professional (PgMP) — Question 191
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance.
To resolve this situation, which of the following must go through critical review and change?
Answer options
- A. Program Benefits Management domain
- B. Stakeholder communications requirements
- C. Program communications report
- D. Program communications management plan
Correct answer: D
Explanation
The correct answer is D, as the Program communications management plan outlines how communication should be handled, which is crucial for resolving the issues caused by ad-hoc requests. The other options do not directly address the management and structure of communication processes, making them less relevant to the solution.