Program Management Professional (PgMP) — Question 189

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.
What should the program manager do to ensure communications on the component projects are consistent?

Answer options

Correct answer: B

Explanation

The correct answer is B because creating a program communications management plan will provide a standardized approach for all component projects, ensuring consistency in communication. Option A is not viable since bringing in a more experienced project manager does not directly address the issue of communication consistency. Option C may lead to mismatches if project A's plan isn't suitable for project B, and option D, while it aims for consistency, lacks a structured approach like a program-wide plan.