Program Management Professional (PgMP) — Question 182

A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?

Answer options

Correct answer: B

Explanation

The correct answer is B because it emphasizes collaboration with the marketing department to gather requirements and involve stakeholders early in the process, which is crucial for the program's success. Option A does not directly engage with the marketing team or the solution, while C, although valuable, may lead to misalignment with the preselected CMS. Option D might not address the immediate needs of gathering requirements effectively.