Program Management Professional (PgMP) — Question 176
A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.
What action should the program manager take first?
Answer options
- A. Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups.
- B. Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes.
- C. Assess the risk of sustained negative media coverage.
- D. Discuss the issues with the governance board to determine next steps.
Correct answer: A
Explanation
The correct answer is A because fostering better relationships with affected stakeholders can lead to more effective communication and resolution of issues. Options B and C are more about assessing the situation rather than taking immediate action, and option D involves seeking approval for next steps rather than addressing the root cause of the negative feedback.