Program Management Professional (PgMP) — Question 130
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.
What is the other part of the review?
Answer options
- A. Tracking and reporting on benefits management plan
- B. Identifying factors influencing delivery of benefits
- C. Demonstrating that other stage gate requirements have been met
- D. Gathering additional stakeholders' requirements
Correct answer: B
Explanation
The correct answer, B, emphasizes the importance of recognizing the elements that impact the delivery of benefits, which is crucial for effective governance. Options A and C focus on reporting and compliance with stage gate criteria, while D is about stakeholder engagement, which is not the primary focus of this review aspect.