Program Management Professional (PgMP) — Question 128
A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified.
Key stakeholders for the program should include which of the following?
Answer options
- A. Potential customers, government regulatory agencies, and competitors
- B. Project management office (PMO), third-party contractors, and agents
- C. Local car dealers, factory workers, and corporate officers
- D. Vice president of logistics, potential customers, and corporate executives
Correct answer: B
Explanation
The correct answer is B because the Project Management Office (PMO), third-party contractors, and agents play critical roles in the execution and management of the project. Options A, C, and D include stakeholders that are important but do not encompass the core management and operational elements that the PMO and contractors provide in a large-scale automotive program.