A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified.
Key stakeholders for the program should include which of the following?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Project Management Office (PMO), third-party contractors, and agents play critical roles in the execution and management of the project. Options A, C, and D include stakeholders that are important but do not encompass the core management and operational elements that the PMO and contractors provide in a large-scale automotive program.