Certified Associate in Project Management (CAPM) — Question 89

Why is working in iterations usually more time consuming than using a predictive life cycle?

Answer options

Correct answer: D

Explanation

The correct answer is D because understanding project requirements can be an extensive process in iterative development. Options A and B are incorrect as they misinterpret the nature of iterations, which often are not longer in duration. Option C is misleading because while a minimum viable product may take time, the primary issue is understanding the requirements.