Certified Associate in Project Management (CAPM) — Question 89
Why is working in iterations usually more time consuming than using a predictive life cycle?
Answer options
- A. Iterations are longer than the execution phase of a traditional project.
- B. Timeboxing increases the time needed to accomplish tasks.
- C. Having a minimum viable product first can take more time.
- D. It takes time to understand what the project needs to deliver.
Correct answer: D
Explanation
The correct answer is D because understanding project requirements can be an extensive process in iterative development. Options A and B are incorrect as they misinterpret the nature of iterations, which often are not longer in duration. Option C is misleading because while a minimum viable product may take time, the primary issue is understanding the requirements.