Certified Associate in Project Management (CAPM) — Question 88

Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

Answer options

Correct answer: D

Explanation

The Schedule Performance Index (SPI) is calculated using the formula SPI = EV / PV. Therefore, SPI = 30 / 15, which equals 2.0. The other options do not reflect this calculation and are incorrect.