Certified Associate in Project Management (CAPM) — Question 88
Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
Answer options
- A. 15
- B. 0.5
- C. 45
- D. 2.0
Correct answer: D
Explanation
The Schedule Performance Index (SPI) is calculated using the formula SPI = EV / PV. Therefore, SPI = 30 / 15, which equals 2.0. The other options do not reflect this calculation and are incorrect.