Certified Associate in Project Management (CAPM) — Question 90

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because it is essential to assess the implications of the proposed feature on the existing project plan before making any decisions. Options A and B do not account for the necessary evaluation of project impacts, while option C focuses on funding without addressing the need for a formal change request process.