Certified Associate in Project Management (CAPM) — Question 79

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

Answer options

Correct answer: A

Explanation

The correct answer is A, Retrospective, as this meeting allows the team to reflect on the past iteration, discuss what went well, and identify areas for improvement. The other options serve different purposes; for instance, a Daily standup is focused on daily progress, while Backlog refinement review and Iteration planning have distinct functions that do not specifically address retrospective analysis.