Certified Associate in Project Management (CAPM) — Question 78

Who is responsible for the business case development document?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Project sponsor, as they are typically responsible for the business case development document, which outlines the justification for the project. The Project manager may oversee the process, while stakeholders and team members contribute input, but the ultimate responsibility lies with the sponsor.