Certified Associate in Project Management (CAPM) — Question 80
A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting.
Which two procedures will the project team perform? (Choose two.)
Answer options
- A. Stakeholder mapping
- B. Issue log update
- C. Deliverable acceptance
- D. Project audit
- E. Risk register tracking
Correct answer: C, D
Explanation
The correct answers are C and D because during the closing stage, the team must ensure that all deliverables are accepted and validated (C) and conduct a project audit to evaluate the overall project performance (D). The other options, such as stakeholder mapping, issue log updates, and risk register tracking, are typically performed in earlier stages of the project.