Certified Associate in Project Management (CAPM) — Question 73

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

Answer options

Correct answer: B

Explanation

The correct answer is B because a root cause analysis identifies the underlying issues that may be causing inefficiencies, which can help stakeholders understand the project's value. Options A and D are important but do not directly address the inefficiencies, while C, a Work Breakdown Structure, is useful for planning but does not address stakeholder concerns.