Certified Associate in Project Management (CAPM) — Question 72
Which tool uses an algorithm based on historical data to calculate cost?
Answer options
- A. Parametric estimating
- B. Relative estimating
- C. Three-point estimating
- D. Analogous estimating
Correct answer: A
Explanation
Parametric estimating is the correct answer because it leverages historical data and statistical relationships to estimate costs. Relative estimating does not specifically rely on historical data, while three-point estimating focuses on optimistic, pessimistic, and most likely estimates. Analogous estimating uses past project data but is less precise than parametric methods.