Certified Associate in Project Management (CAPM) — Question 74

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

Answer options

Correct answer: A

Explanation

The correct answer is A because the business analyst, project manager, and stakeholders collectively ensure that all key members are included in communication. Options B and C exclude essential roles that may provide critical insights, while option D limits the review to just the business analyst, which is insufficient for comprehensive communication management.