Certified Associate in Project Management (CAPM) — Question 59
A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project, of what should the project manager be aware?
Answer options
- A. Demands on the same resources
- B. Requirements that impact the scope
- C. Uncertainty of emerging issues
- D. Project charter
Correct answer: A
Explanation
The correct answer is A, as demands on the same resources can lead to conflicts and delays in project timelines. While requirements, uncertainties, and the project charter are important, they do not directly address the need to manage competing resource demands which can severely affect project execution.