Certified Associate in Project Management (CAPM) — Question 58
A project team of telecommuters located in three different time zones regularly misses project deadlines. Daily meetings often start and end with the same person talking and the rest of the team listening. The project manager determines that communication among team members must be addressed.
What communication step is missing from the daily meetings?
Answer options
- A. Interpersonal communication
- B. Feedback/response communication
- C. Push communication
- D. Pull communication
Correct answer: B
Explanation
The correct answer is B, as feedback/response communication is essential for ensuring all team members can engage and provide input during meetings. Without this interaction, discussions become one-sided, hindering effective collaboration. Options A, C, and D do not specifically address the need for active participation and response from all members, which is critical in a team setting.