Certified Associate in Project Management (CAPM) — Question 51
Which of the following is an output of the Perform Integrated Change Control process?
Answer options
- A. Cost-benefit analysis
- B. Updated project charter
- C. Approved change request
- D. Multicriteria decision analysis
Correct answer: C
Explanation
The correct answer is C, as the Perform Integrated Change Control process is responsible for reviewing and approving changes, which results in an approved change request. Options A, B, and D are not direct outputs of this process; they may be used in various stages of project management but do not specifically relate to the change control process.