Certified Associate in Project Management (CAPM) — Question 51

Which of the following is an output of the Perform Integrated Change Control process?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the Perform Integrated Change Control process is responsible for reviewing and approving changes, which results in an approved change request. Options A, B, and D are not direct outputs of this process; they may be used in various stages of project management but do not specifically relate to the change control process.