Certified Associate in Project Management (CAPM) — Question 50

What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?

Answer options

Correct answer: B

Explanation

The correct answer is B, Define Activities, as it specifically focuses on identifying and detailing the tasks required to deliver project outputs. The other options refer to different aspects of schedule management: A is about establishing how to manage the schedule, C is about creating the overall timeline, and D involves estimating how long each task will take, but none of those define the individual activities themselves.