Certified Associate in Project Management (CAPM) — Question 49
When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?
Answer options
- A. Iterative scheduling with backlog
- B. On-demand scheduling
- C. Life cycle scheduling with backlog
- D. Defining iterative activities
Correct answer: A
Explanation
The correct answer is A, as iterative scheduling with backlog involves continuously refining and prioritizing user stories before construction. Options B and C do not capture the essence of refining backlog items specifically for upcoming iterations, while D does not adequately describe the scheduling method in relation to user stories.