Certified Associate in Project Management (CAPM) — Question 52
Which of the following set of items belongs to the communications management plan?
Answer options
- A. Escalation processes and meeting management
- B. Project schedule and glossary of common terminology
- C. Escalation processes and stakeholder communication requirements
- D. Interactive communication model and information to be communicated
Correct answer: C
Explanation
The correct choice, C, accurately identifies elements that are crucial for managing communication with stakeholders. Option A focuses more on processes, while B includes unrelated project management elements, and D mentions communication models that are not specifically part of the communications management plan.