Certified Associate in Project Management (CAPM) — Question 476
One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?
Answer options
- A. It represents how and when the project will deliver the products, services, and results defined in the project scope
- B. It creates a formal record of the project and shows the organizational commitment to the project
- C. It describes how the scope will be defined, developed, monitored, controlled, and validated
- D. It provides the needs of a stakeholders or stakeholder group
Correct answer: A
Explanation
The detailed plan primarily illustrates the timeline and methodology for delivering the project's defined outcomes, making option A the correct choice. Options B, C, and D describe other aspects of project management but do not specifically address the detailed plan's main purpose.