Certified Associate in Project Management (CAPM) — Question 477

What communication methods would a project manager use for overall effective project communication?

Answer options

Correct answer: B

Explanation

The correct answer is B because interactive communication, push communication, and pull communication are essential methods that cater to different stakeholder needs. Options A, C, and D incorrectly include interpersonal communication, which is not classified as a primary communication method in project management.