What communication methods would a project manager use for overall effective project communication?
Answer options
- A. Interactive communication, push communication, interpersonal communication
- B. Interactive communication, push communication, pull communication
- C. Push communication, pull communication, interpersonal communication
- D. Pull communication, interactive communication, interpersonal communication
Correct answer: B
Explanation
The correct answer is B because interactive communication, push communication, and pull communication are essential methods that cater to different stakeholder needs. Options A, C, and D incorrectly include interpersonal communication, which is not classified as a primary communication method in project management.