Certified Associate in Project Management (CAPM) — Question 467
To which knowledge area does the Collect Requirements process belong?
Answer options
- A. Quality Management
- B. Scope Management
- C. Cost Management
- D. Integration Management
Correct answer: B
Explanation
The Collect Requirements process is part of Scope Management because it focuses on defining and documenting stakeholders' needs and requirements for the project. The other options, such as Quality Management, Cost Management, and Integration Management, relate to different aspects of project management and do not specifically address the gathering of requirements.