Certified Associate in Project Management (CAPM) — Question 459

What should a project manager do to prepare a risk management plan in a project with a lot of technical uncertainty?

Answer options

Correct answer: A

Explanation

The correct answer is A, as obtaining expert judgment provides valuable insights and informed perspectives to effectively identify and manage risks associated with technical uncertainty. Options B and C may not provide the necessary depth of knowledge required for complex technical issues, while option D is impractical as delaying the project could lead to increased costs and missed opportunities.