Certified Associate in Project Management (CAPM) — Question 460
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
Answer options
- A. Stakeholder engagement plan and organizational process assets
- B. Project schedule and stakeholder register
- C. Quality management plan and risk register
- D. Basis of estimates and scope baseline
Correct answer: A
Explanation
The correct answer is A because the stakeholder engagement plan provides insights into how to communicate with stakeholders, and organizational process assets offer historical data and templates that can guide communication strategies. The other options include documents that are not specifically focused on communication management, making them less relevant inputs for this particular plan.