Certified Associate in Project Management (CAPM) — Question 442

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Answer options

Correct answer: A

Explanation

Verified deliverables are the outputs of the verification process and serve as an essential input for formal acceptance. Validated deliverables refer to those that meet the requirements but have not yet been accepted, while accepted deliverables imply approval, which occurs after this process. Completed change requests are important for managing project scope but are not directly an input for the acceptance of deliverables.