Certified Associate in Project Management (CAPM) — Question 443
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
Answer options
- A. Hold a face-to-face meeting with the project manager and warn them
- B. Point the director to a link where they can take a look at the reports
- C. Invite stakeholders to attend monthly progress review meetings
- D. Ask the project manager to update the monthly status report distribution list
Correct answer: C
Explanation
The correct answer is C because involving stakeholders in monthly progress review meetings facilitates communication and transparency, allowing concerns to be addressed collaboratively. Option A may create tension, while B does not directly engage the director’s concerns, and D does not involve stakeholders in the conversation.