Certified Associate in Project Management (CAPM) — Question 441

Which is the tool or technique that is used to obtain the list of activities from the work packages?

Answer options

Correct answer: D

Explanation

The correct answer is D, Decomposition, as it is specifically used to break down work packages into smaller, manageable activities. Options A, B, and C refer to different processes in project management, but they do not serve the purpose of directly obtaining a list of activities from work packages.