Certified Associate in Project Management (CAPM) — Question 440
Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?
Answer options
- A. Project Schedule Management
- B. Project Scope Management
- C. Project Resource Management
- D. Project Integration Management
Correct answer: D
Explanation
The correct answer is D, Project Integration Management, as it encompasses the coordination of all aspects of a project, including its life cycle phases. The other options focus on specific areas like scheduling, scope, and resources, but do not address the overall integration of project components.