Certified Associate in Project Management (CAPM) — Question 439
During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
Answer options
- A. Change request
- B. Risk response
- C. Risk management plan
- D. Lessons learned
Correct answer: A
Explanation
The correct answer is A, Change request, as this process involves formally requesting modifications to address defects. Options B and C relate to managing risks rather than rectifying defects, while D pertains to documenting insights gained, not the act of fixing the defect.