Certified Associate in Project Management (CAPM) — Question 421
Why is tailoring in a project necessary?
Answer options
- A. Requirements keep changing
- B. An artifact must be produced
- C. A tool or technique is required
- D. Each project is unique
Correct answer: D
Explanation
The correct answer is D because each project has unique attributes that may require a different approach or methodology to ensure success. Options A, B, and C are not as fundamental, as while requirements may change, artifacts need to be produced, and tools or techniques may be necessary, they do not capture the essence of individual project uniqueness.