The primary purpose of the stakeholder register is to:
Answer options
- A. Record stakeholder issues on the project
- B. Maintain lessons learned earlier in the project
- C. Maintain a list of all project stakeholders
- D. Document change requests and their status
Correct answer: C
Explanation
The correct answer is C because the stakeholder register is specifically designed to maintain a comprehensive list of all stakeholders associated with the project. Options A, B, and D refer to different project management documents and processes that do not represent the primary purpose of the stakeholder register.