Certified Associate in Project Management (CAPM) — Question 419

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

Answer options

Correct answer: D

Explanation

Conducting a quality audit is the most effective way to ensure that project activities align with organizational and project policies, as it involves a systematic review of processes. The other options, while useful for assessing various aspects of quality, do not specifically ensure compliance with policies and procedures.