Certified Associate in Project Management (CAPM) — Question 419
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
Answer options
- A. Look at the quality metrics
- B. Validate the scope
- C. Review the quality checklist
- D. Conduct a quality audit
Correct answer: D
Explanation
Conducting a quality audit is the most effective way to ensure that project activities align with organizational and project policies, as it involves a systematic review of processes. The other options, while useful for assessing various aspects of quality, do not specifically ensure compliance with policies and procedures.