Certified Associate in Project Management (CAPM) — Question 422
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
Answer options
- A. Power interest grid
- B. Stakeholder cube
- C. Salience model
- D. Directions of influence
Correct answer: C
Explanation
The Salience model is specifically designed to assess and categorize stakeholders based on their perceived power, urgency, and legitimacy. The Power interest grid and Stakeholder cube are different frameworks that do not focus on these three factors in the same way, while Directions of influence does not relate directly to classifying stakeholder attributes.