Certified Associate in Project Management (CAPM) — Question 392

How can a project manager evaluate project team development?

Answer options

Correct answer: A

Explanation

The correct answer, A, is valid because team performance assessments offer a structured way to evaluate the overall effectiveness and development of the team. Option B, while engaging, does not specifically measure development, and options C and D focus on individual evaluations and recognition rather than the team as a whole.