Certified Associate in Project Management (CAPM) — Question 393
Which of the following lists represents the outputs of the Monitor Communications process?
Answer options
- A. Project communications, project management plan updates, project documents updates, and organizational process assets updates
- B. Work performance information, change requests, project management plan updates, and project documents updates
- C. Communications management plan, project management plan updates, work performance report, and project documents update
- D. Stakeholder engagement plan, change requests, project management plan updates, and project documents updates
Correct answer: B
Explanation
The correct answer is B because the Monitor Communications process outputs include work performance information, change requests, project management plan updates, and project documents updates. The other options do not accurately reflect the outputs of this process, as they include items that are not outputs or mix different processes' outputs.