Certified Associate in Project Management (CAPM) — Question 391
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
Answer options
- A. create the project management plan.
- B. identify the project objectives.
- C. review and update stakeholder engagement.
- D. create the schedule baseline.
Correct answer: C
Explanation
The correct answer is C, as reviewing and updating stakeholder engagement is crucial during phase transitions to ensure continued support and communication. Options A and D pertain to earlier project planning activities, while B focuses on defining objectives, which should already be established before moving to the next phase.