Certified Associate in Project Management (CAPM) — Question 390

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Answer options

Correct answer: D

Explanation

The correct answer is D, Develop Team, because this process involves enhancing the team's skills and fostering collaboration, which aligns with co-location and training. The other options focus on different aspects of resource management, such as acquiring resources (A) or maintaining and monitoring them (B and C), which do not directly involve team development activities.