Certified Associate in Project Management (CAPM) — Question 389
Which of the following tasks focuses on decomposing work packages?
Answer options
- A. Adjust duration estimates
- B. Define activities
- C. Complete rolling wave planning
- D. Develop milestone list
Correct answer: B
Explanation
The correct answer is B, as defining activities is the process of identifying and detailing the specific tasks that need to be completed, effectively breaking down work packages. The other options do not specifically involve the decomposition of work packages; adjusting duration estimates focuses on time management, while developing milestone lists and completing rolling wave planning are about scheduling and planning respectively.