Certified Associate in Project Management (CAPM) — Question 389

Which of the following tasks focuses on decomposing work packages?

Answer options

Correct answer: B

Explanation

The correct answer is B, as defining activities is the process of identifying and detailing the specific tasks that need to be completed, effectively breaking down work packages. The other options do not specifically involve the decomposition of work packages; adjusting duration estimates focuses on time management, while developing milestone lists and completing rolling wave planning are about scheduling and planning respectively.