Certified Associate in Project Management (CAPM) — Question 388
Which key benefit can a project manager obtain by identifying stakeholders?
Answer options
- A. Identify the appropriate focus for engagement of each stakeholder
- B. Assess the risk exposure for each stakeholder
- C. Map stakeholder power and influence grid
- D. Identify the appropriate channels of communication with all stakeholders
Correct answer: A
Explanation
The correct answer is A because identifying stakeholders allows a project manager to focus their engagement strategies effectively. Options B, C, and D, while important, do not directly relate to the primary benefit of engagement focus, which is crucial for stakeholder management.