Certified Associate in Project Management (CAPM) — Question 379
A project manager is performing a specific process and has a list of accepted deliverables. One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables. Which process is being referred to?
Answer options
- A. Control Quality
- B. Validate Scope
- C. Validate Quality
- D. Control Scope
Correct answer: B
Explanation
The correct answer is B, Validate Scope, as this process involves confirming that the deliverables meet the requirements and have been accepted by stakeholders. Control Quality (A) focuses on measuring and monitoring project results to ensure they meet quality standards, while Validate Quality (C) is not a recognized process, and Control Scope (D) is about managing changes to the project scope.