Certified Associate in Project Management (CAPM) — Question 378
Project reporting is a tool that is most closely associated with which process?
Answer options
- A. Communicate Plan
- B. Manage Communications
- C. Report Performance
- D. Control Communications
Correct answer: B
Explanation
The correct answer is B, Manage Communications, because this process involves the creation, distribution, and management of project information, including reporting. The other options, while related to communication, do not specifically focus on the management aspect of project reporting.